November 24, 2026

Brownfield Eligibility

Turning Environmental Due Diligence into Project Opportunity
Field technician wearing a high visibility safety vest and protective gloves examines soil samples using a soil color chart beside a shovel at a project site. Field technician wearing a high visibility safety vest and protective gloves examines soil samples using a soil color chart beside a shovel at a project site.

By Jack Belvedere, ASTM-CEP, Charlie Tiller, PG (MN), and Rachel Ludicke, TCEQ-CAPM

For renewable energy developers, environmental due diligence is typically associated with identifying potential constraints. Under the Inflation Reduction Act (IRA), however, certain environmental conditions may also create an opportunity. 

The IRA established incentives for qualifying energy projects located within designated “energy communities,” including certain brownfield sites. As a result, the IRS Brownfield Safe Harbor provisions can allow qualifying renewable energy projects to receive up to a 10% Energy Community Bonus Credit beyond existing investment and production tax credits. Determining whether a property satisfies the applicable criteria, however, is more complex than simply dubbing it a “brownfield.” The IRS establishes specific conditions for brownfield eligibility, which may differ subtly from how regulators and industry experts have historically used the term. 

For developers, understanding that distinction early in the process can matter. Environmental information already available for a property—or information gathered through additional due diligence—may help determine whether a project has a viable path toward documenting brownfield eligibility. 

That is the question our clients increasingly began bringing to us: We think we may have a brownfield. Can you help us determine whether it qualifies? 

Understanding the Path to Brownfield Eligibility 

The IRS framework identifies three tests for establishing whether a project property may qualify as a brownfield site: a previous brownfield assessment within a delegated “Superfund” regulatory program, a Phase II Environmental Site Assessment (ESA) compliant with ASTM E1903, or, for certain projects with a nameplate capacity of not greater than 5MW (AC), an ASTM-compliant Phase I ESA that identified a Recognized Environmental Condition (REC). To satisfy the IRS Safe Harbor, the findings must be consistent with the IRS brownfield definition, which specifies that the presence or potential presence of a hazardous substance, pollutant or contaminant “may complicate the expansion, redevelopment, or reuse of the property.” 

Each pathway requires understanding not only what environmental information exists, but how that information relates to the IRS criteria and the client’s project plans. 

A developer, for example, may already have historical records, a Phase I ESA, sampling results, or a Phase II ESA prepared for another purpose. The question becomes whether that body of information supports a brownfield eligibility determination and, if it does not yet provide an answer, what additional investigation may be appropriate. 

Rather than addressing those pieces independently, we developed the Westwood Brownfield Eligibility Evaluation to consider them systematically within the context of the IRS requirements. 

The evaluation organizes available environmental information and provides one potential pathway for documenting whether applicable IRS criteria are satisfied. It can also identify information gaps and potential next steps. Our role is environmental and technical, consistent with Westwood’s expertise; the evaluation is not intended to provide tax or legal advice. 

Bringing the Question Forward in Development 

Developers do not necessarily need to wait for formal environmental investigations to be complete before evaluating potential brownfield eligibility. 

We offer a Preliminary Brownfield Eligibility Evaluation as a desktop review that can complement early-stage project evaluation, including a Critical Issues Analysis. For projects further along, a comprehensive Brownfield Eligibility Evaluation can incorporate formal environmental due diligence and other available project information.  

Within our team, the two approaches have affectionately become known as the “humble-BEE” and “honey-BEE” reports—a play on the Brownfield Eligibility Evaluation acronym. For clients, however, the important distinction is simpler: the scope can be matched to the information available and the project’s stage of development. 

That flexibility matters because the potential opportunity is not identical for every project. Property configuration, project scale, existing environmental information, and other factors can influence whether further evaluation makes sense. Even when an evaluation does not ultimately support brownfield eligibility, understanding environmental conditions earlier can better prepare a development team for issues that may need to be addressed as the project advances.  

The emergence of this incentive has introduced a relatively new question into renewable energy due diligence. Our clients began asking it early, and Westwood invested in understanding how the environmental pieces fit together so we could help them evaluate the opportunity while it is still actionable. 

For developers evaluating potential brownfield eligibility, the starting point may be information they already have. The next step is understanding what that information means. 

To discuss a preliminary or comprehensive Brownfield Eligibility Evaluation for an upcoming project, connect with Jack Belvedere, Charlie Tiller, or Rachel Ludicke. 

Keep Reading

Join our talented team.
Partner with us on your next project.
Westwood Footer Image Westwood Footer Image