Pennsylvania Transmission Line Re-Conductor

0045647_1.jpg
0045647_2.jpg
0045647_3.jpg
0045647_5.jpg
0045647_6.jpg
Location
Macungie, Pennsylvania
Client
Investor-Owned Utility
Scope

Relocated existing transmission, 20 circuits, 16–230 kV over 4.3 miles.

Roles
  • Custom Steel Pole and Arm Design
  • Engineering
  • Soil Borings
  • Bill of Materials
  • Ultrasonic Scanning of Steel Poles
  • Transmission Engineering
  • Foundation Design
  • Construction Sequencing
  • PLS-CADD Modeling
  • Construction
  • High-Density LiDAR of structures